SELECTBOARD ANNUAL REPORT
The
Selectboard typically meets on the second and fourth Monday
of each month at 7:30 p.m. at the Waitsfield Town Office, though
some of the start times varied this year. Citizens are
encouraged to contact Town Administrator Valerie Capels to confirm
meeting dates or to have a matter placed on the agenda. Our
meetings are open to the public and citizens are invited to
attend. We are also pleased that most of our meetings are filmed
for broadcast on Mad River TV on channel 60. Some of the
Selectboard's major work is discussed below.
Municipal
Water and Wastewater Projects Update. Significant progress
was made through 2007 to advance both water and wastewater projects
to the point where they are now on the ballot this year for
bond funding. Phelps Engineering continued to refine design
plans and project costs for both the water and wastewater systems
and began preparing permit applications. The well was
drilled in the Reed Road, tests were concluded, and a wellhead
management plan was produced. The Town began efforts to
acquire the necessary wellhead protection area and an easement
across private property. A public meeting was held on
June 14 to provide citizens with a wide range of information
about both projects. The Town received a municipal planning
grant to help fund public information efforts. Draft connection
policies have been drafted that will need to be refined as the
project moves forward. In an effort to get a more firm
sense of the number of property owners interested in connecting
to either system, the Selectboard offered an incentive of a
reduced connection fee if people responded by a certain date.
The project plans have been coordinated with the Irasville
and Village sidewalk improvement project and the Route 100 paving
project and construction is slated to begin in 2008.
Route
100 Transportation Path Project Update. Final designs
for the Route 100 Transportation Path, a sidewalk and bike lanes
project along Main Street from Bragg Hill Road to the Waitsfield
Elementary School, are nearing completion and are now wending
their way through the VTrans Right-of-Way Division for review
and ultimately approval. Selectman Charlie Hosford continued
to work closely with Municipal Project Manager Kevin Russell,
engineering consultant Mark Bannon, and State officials to keep
the project moving forward. Construction of the project is planned
for 2009, followed by the Route 100 repaving in 2010. The Town
is making a concerted effort to coordinate the sidewalk project
with the water and wastewater projects and repaving of Main
Street. It is our goal to do these projects in a logical sequence
to be most cost effective and the least disruptive to citizens.
Village Center Designation Approved.
Waitsfield's Village Center Designation
application was approved in September by the Vermont Downtown
Board, which means that the following benefits will be available
to owners of historic properties in Waitsfield Village for at
least the next three years:
- 10% tax credit for substantial rehabilitation of a historic
building;
- 25% tax credit for façade improvements; and/or
- 50% tax credit for code improvements.
Additional
benefits to the Town include priority consideration for all
future municipal planning and CDBG grants, consideration and
priority by the State Building Department when leasing or constructing
buildings, and special assessment benefits. For more info, visit
www.waitsfieldvt.us/about/villagecenter.cfm.
Growth
Center Designation and TIF District Applications Moving Forward.
Village Center Designation is also an important step toward
our Growth Center Designation and TIF district applications.
The Town hired PlaceSense and the Vermont Forum on Sprawl
(now Smart Growth Vermont) this year to work with the Planning
Commission and other community leaders to develop 20-year projections,
build-out analyses, financial projections, and the other elements
required for the applications. If successful, a tax increment
finance (TIF) district would allow the Town to redirect that
proportion-or increment-of property tax revenue generated from
new development in the designated area to help fund infrastructure
improvements that support the growth center, such as the water
and wastewater projects. The state legislature has limited
the number of municipalities to ten statewide that may obtain
approval to establish a TIF district, so time is of the essence
to ensure our place in line. Waitsfield's Town Plans have
identified Irasville and Waitsfield Village as a "growth
center" long before Vermont's Growth Center program was
established to reward communities with financial incentives,
policy priorities, and regulatory tools that plan for compact
smart growth in designated areas.
Gravel
Pit. A request for proposals was released in the fall
and as 2007 was drawing to a close, two consultant firms were
being considered to work with the Town to develop a site design
and assist with permitting of the gravel pit. Phelps Engineering
was selected and site analysis work will begin in spring 2008.
The Selectboard will be very interested to meet with neighbors
about any issues or concerns that might arise.
Emergency
Generator. In 2006, voters authorized the Selectboard
to "
purchase a generator for emergency shelter use
at the Waitsfield Elementary School at a cost not to exceed
$35,000; to appropriate $5,000 for such purpose and to approve
placement of said funds into a reserve account if not expended
in 2006; and to authorize financing an amount not to exceed
$30,000 to fund the balance of said purchase to be repaid over
a period not to exceed 5 years and on such other terms as the
Selectboard shall negotiate." After considerable
discussion and consideration of alternatives, the Selectboard
supported the installation of a 100 KW Kohler generator located
behind the General Wait House, where it serves not only the
Elementary School, but also the Wait House and possibly Mad
River Valley Community Health Center. The
Town received a $15,000 grant from the Vermont Department of
Emergency Management (VEM), which brought the total cost of
the project to the Town to $27,723. A proposal was submitted
to VEM in November seeking an additional $7,000 in 50/50 matching
grant funds to connect the Health Center to the third switch
of the generator. If awarded, the Health Center will pay the
required 50% match.
Paving
and Road Projects. It was a maintenance year with
no major paving projects in 2007 and the Road crew continued
to do an excellent job at general maintenance, including road
rebuilding, grading, culvert replacement, wood bridge reconstruction,
and brush cutting. The Department was kept especially
busy this past winter, one of the top snowiest winters ever,
particularly in the aftermath of the Valentine's Day storm that
dumped 39 inches. Several freeze-thaws extended our mud season
more than usual. Parsonage Lane was repaved and restriped
and Joslin Hill Road was shimmed to help smooth out the ruts.
The Road Department began its replacement of the wooden
road name signs with E-911 compliant green reflective signs,
focusing first on intersections along Route 100. Replacement
of the remaining signs will continue in 2008, starting along
the East Warren Road and then on to other intersections. Although
Rodney Jones' mechanical skills have helped keep the equipment
running and repair costs down, two vehicles did need to be replaced.
The 16-year old backhoe was replaced with a more efficient
machine that will provide better roadside ditch and culvert
maintenance. And one of the dump trucks was replaced with
not only the latest in green technology but a larger size that
will enable the Department to move more material with fewer
trips.
Tree
Project. As part of our Scenic Road Management Plan,
we undertook removal of numerous dead trees within the public
right of way. In several instances, private land owners
have made contributions to the Town to help defray the cost
of tree removal and we greatly appreciate this cooperative effort.
Special thanks to Charlie Hosford and Paul Hartshorn for their
collaboration on this project.
The
1833 Covered Bridge. In response to the growing concern
about the well-being of the Waitsfield 1833 Covered Bridge,
the Town submitted an application to the VTrans Enhancement
Grant program seeking almost $273,000 in federal funds to address
the cantilevered sidewalk on the north side of the Covered Bridge
and repair the bridge's abutments. We learned in January
2008 that the application has been fully funded. The Town
will need to provide approximately $70,000 in matching funds,
which has been reflected in the Capital Budget and Plan. The
Covered Bridge Repairs Reserve Fund is proposed to be resurrected
in 2008 to begin setting aside monies for this work. Even
if the grant had not been funded, the funds would be necessary
to address the bridge's structural issues. The 1833 Village
Covered Bridge is confirmed to be the oldest covered bridge
in Vermont still in everyday use and the Town is committed to
preserving this historic Vermont landmark.
Law
Enforcement. The Town continues to have a great working
relationship with the Washington County Sheriff's Department.
We contract for 40 hours of coverage per week and our local
constable, Peter Laskowski, provides 2/3 of this with 24 hours
of patrolling per week. The patrols provide effective
deterrent to traffic violations and a community law enforcement
presence that works as a first responder in cooperation with
the Vermont State Police. This allows quicker law enforcement
response to serious complaints. Deputy Sheriff Laskowski
works closely with the Neighborhood Watch Programs in the MRV
towns, which provide a very valuable source of information and
deterrent to local crime activities.
Garage
Lighting Replacement. In spring 2007, the Town took
the initiative to replace the outdated and ineffective lighting
fixtures in the Town Garage with Super T8 energy efficient fixtures.
Even with the rebate of $1,400 from Efficiency Vermont,
the $4,700 project exceeded our $2,500 budget for energy efficiency
projects by $800.
Environmental
and Safety Audits.
Also this spring, the Town invited Vermont League of Cities
and Towns' Loss Control Consultant to conduct a safety audit
of the Town buildings. Overall, the Town Garage, Town
Office, Fire Station, and Wait House scored high marks and opportunities
for improvement were quickly addressed. One improvement
was the purchase of a flame-proof metal cabinet for storage
of flammable materials. The only recommendation we are
unable to comply with in the immediate future is the separation
of the Town Garage staff's eating area from the work area. Their
refrigerator and lounge/break area is located on a mezzanine
floor above the shop. The way to address that would be
to somehow build a separate room. John Daly, Compliance
Specialist from the Agency of Natural Resources also conducted
an environmental audit of the Town Garage. No infractions
were found, and it was an opportunity for staff to be refreshed
on proper procedures for handling hazardous materials.
Energy
Coordinator and Committee. Waitsfield resident Dennis
Derryberry was appointed to be Waitsfield's first Energy Coordinator
in May, which was followed soon after by the formation of the
new Waitsfield Energy Committee. Members so far include
Selectmen Sal Spinosa, who was elected Chair, Charlie Hosford,
and Paul Hartshorn. The focus of the committee has been
to improve the energy efficiency of our town-owned facilities,
specifically the Town Garage and the General Wait House.
Future efforts are likely to include public outreach about town-wide
energy efficiency issues, updating the Energy section of the
Town Plan, and exploring cost-effective ways Town facilities
might even produce energy.
Better
Back Roads Grants. With help from the Friends of the
Mad River, Waitsfield was awarded a $4,000 grant from the Better
Back Roads program to inventory road-related erosion locations
and develop a five year capital plan to prioritize and fund
needed improvements. The final product will be a map identifying
problem locations, a report, and a proposed five year capital
plan to address improvements. The Town's 25% required
match will be in the form of Town staff's time. The Town
was also awarded $6,946 through the BBR program to address drainage
and erosion issues on Dana Hill that are causing sediment to
cross Route 17 and go into the Mill Brook. Both of these
projects will not get underway, however, until spring 2008,
so these grant awards are shown in the 2008 budget as Road Department
revenue. The Selectboard wishes to thank the Friends of
the Mad River and Miranda Lescaze, former FOMR Director, for
her initiative in tracking down these resources on behalf of
the Town.
Town
Office Space Improvements. Changes in Town Office
personnel last year prompted the need to re-evaluate and reconfigure
how some space is used. The Selectboard wishes to acknowledge
and thank Selectman Charles Hosford for the considerable time
and expertise he donated to the Town in building shelving and
other accoutrements to improve office operations. Thanks are
due also to the Road Department for their help in moving the
permit files to where part of the front counter used to be,
which greatly improved workflow and the public's access to records.
New
Planning & Zoning Administrator. Zoning Administrator
David Jescavage moved on to become the Town Administrator in
Highgate in June 2007. Following an extensive recruitment
process, the Selectboard was pleased to appoint Waitsfield's
own Blaine Laskowski to serve as Waitsfield's new Planning and
Zoning Administrator. The position was restructured to
part-time and e-mail address changed to pza@madriver.com.
Move
to a Development Review Board (DRB). The formation
of the DRB was accomplished in March and all indications are
that the transition was a success. The DRB replaced the
Zoning Board of Adjustment and assumed the development review
duties of the Planning Commission, which in Waitsfield was limited
to subdivision review. With the exception of one remaining
subdivision application in its pipeline, the PC will no longer
be reviewing subdivisions, allowing it to focus attention on
long-range planning, the development of regulatory amendments,
and policy creation on a range of subjects. The Selectboard
met jointly with members of the Planning Commission and the
DRB in November and discussed such matters as the proposed subdivision
regulations, litigation, and the need to cultivate additional
volunteers willing to serve on the boards.
Web
Site. Waitsfield's official Web site www.waitsfieldvt.us
was launched in April 2007, with new content added on a regular
basis. Meeting agendas are posted, often with links to
documents that will be discussed that citizens can conveniently
access. Various ordinances, Town policies, and permit
application forms can be found in the Rules
and Regs section; the Town Plan, reports, archives, and
other documents can be found in the Document
Library; and soon the Town Report and budget information
will be available there in electronic form. Though it
is still a work in progress, our goal is for the Web site to
become a reliable resource where citizens can find the information
they need about the community, goings-on, Town operations, and
opportunities to become involved.
Staff
and Volunteers. The Selectboard wishes to acknowledge
and thank the Town staff for their efforts to keep operations
moving smoothly and special thanks to all the citizens who volunteer
countless hours of time and other resources serving on boards,
committees, commissions, and task forces.
Respectfully
submitted,
Elwin Neill, Jr., Chair
Charles Hosford
J. Leroy Hadden, D.V.M.
Paul Hartshorn
Sal Spinosa