|
|
|
Waitsfield
Municipal Water Project
Costs  |
Water Page |
Once the municipal water system is constructed, costs to customers
will include yearly fixed and variable costs, as well as one-time
costs associated with connecting to the system. Fixed costs
are those that must be paid, even if not a single drop of water
is used, such as the debt service on loans. This cost is represented
by the base fee. The more customers
that sign on to the system, the lower the fixed costs are for each.
Variable costs reflect the amount of water actually used,
which will be measured by a meter. This is called the use
fee. One-time costs include the cost to extend the water
line from the right-of-way to the building as well as the connection
fee, which, among other things, covers the cost of a meter.
These costs and more are explained in detail below.
Table 1. Summary
of Initial Costs
| Initial Costs |
| Construction
costs |
$5.2 M
|
| Construction
contingency (10%) |
$0.5 M
|
| Other
costs (engineering, legal, admin., easements, etc.) |
$1.9 M
|
| Projected
Initial Costs |
$7.6 M
|
| Off-setting Revenues |
| Fed. State & Tribal
Assist. Grant (STAG) - secured |
($1.98 M)
|
| USDA Rural Development
Grant (RD) |
($2.5 M)
|
| Connection fees to pay
for meters |
($0.1 M)
|
| Total off-setting revenue |
($4.58 M)
|
Projected
local share of initial costs
to be paid back with a loan from USDA Rural Development
at 3.75% over 40 years. |
$3.014 M
|
|
Project
Construction Costs
The initial
cost to construct the water system is projected to be $7.6 million.
This includes costs for construction, source exploration and
drilling, legal services, administration, easements, engineering,
permitting and other related costs. This cost will be offset
by grants and a portion of connection fees, resulting in a "local
share" that will be rolled into a long-term loan as shown in Table
1.
The decision to include fire protection adds approximately $1.36
million to the cost of the project. This includes the cost
of 16 hydrants (approx. $3,000 each, installed), a 12-inch water
main instead 4-inch or 6-inch lines, and a 400,000 gallon water
storage tank rather than a 100,000 gallon tank.
Planning,
Design, & Engineering Costs
About $500,000
has already been spent over the 10+ years since the planning, design,
and engineering work began. This includes costs associated
with exploring water sources, drilling test wells, hydrogeologic
studies, construction of the Reed Road well, preliminary design
and engineering studies, surveying, and permitting, easements, legal
services, and helping to assemble the funding packages from state
and federal sources. These costs, as well as projected future
costs for final engineering and construction services are projected
in the construction costs and the total bond amount.
Table
2. Summary of Annual Costs
| Annual
Costs |
| Debt
service (40-yr Rural Dev. loan) |
$146,000
|
| Operation
& Maintenance (O&M) |
$50,000
|
| Projected
Annual Costs |
$198,000
|
| Annual
Revenues |
| Base
Fee (to retire the debt service) |
($146,000)
|
|
Use Fee (to offset annual O&M costs) |
($50,000)
|
| Projected
Annual Revenue |
($198,000)
|
|
Annual
Project Costs
In addition
to the debt service to pay back the long term construction loan,
annual costs will include operation and maintenance (O&M) costs
such as labor, utilities, testing, and administrative costs such
as billing and insurance. These projected costs are shown
in Table 2.
The costs include repayment of two no-interest loans totaling $311,000
extended to the Town for the planning and engineering.
If the project does not go forward, payback is scheduled to
begin in 2012 over 5 years and would require annual payment of approximately
$62,000.
Annual
Project Revenues
Revenues to
pay the annual debt service and O&M (operation and maintenance)
costs will come from the connected customers, which includes two
components: a Base Fee and a Use Fee.
|
Equivalent
Residential Unit = a typical 3-bedroom house or 245 gallons
per day.
|
Base
Fee
The Base Fee
shown is the amount each customer is projected to pay toward debt
service. The base fee will be charged as a multiple of the
property's designated ERU value (i.e. a property with 2 ERUs will
pay twice the amount as a property with 1 ERU).
Metered
Use Fee
The Use Fee
shown is the average amount a typical customer will contribute to
offset the annual O&M costs and is expected to be based on the amount
of water used. Properties with higher water uses will pay
an equitably higher share toward the O&M costs. With this
model, the use charge would be in the range of $3 per thousand gallons
of water used. The rate schedule will not be finalized until
the project is in construction, as it is anticipated some properties
will elect to wait until the pipeline is being installed past their
home to agree to connect.
Reserve
Fund
A reserve fund
is needed to provide a contingency for replacement of equipment
and other incidental costs that are not budgeted in a given year.
A minimum fund balance (typically 10% of the annual debt service)
is required as a condition of the long-term construction loan to
ensure that annual debt service payments can be made. The
Reserve Funds will be established with a portion of the initial
connection fees; future connection fees and accrued interest will
provide additional revenue sources for the systems.
One-Time
Costs to Customers
During
the initial construction phase and each time a new customer connects
to the system, two one-time costs must be included. Table
3 provides a breakdown of the one-time and annual costs for
a typical household that connects to the water system. Figure
1 shows that as more customers connect to the system, both the
base fee and use fees will be reduced as the debt service and annual
costs are spread over a wider base.
Table
3. Example: Single Family Home in Service Area
| One-Time
Costs |
Before
12/31/09
|
After
12/31/09
|
| New
connection fee |
$500
per ERU
|
$2,000
per ERU
|
| Stub
to right-of-way(1) |
Included
for connecting customers(3)
|
$2,000
- $4,000
|
| Construction
of service from ROW to structure(2) |
$30
to $75 per linear foot Example: 30 ft would be $900
to $2,250
|
Total
one-time cost
(for 30 ft example) |
$1,400
- $2,750
|
$4,900
- $8,250
|
| Annual
Costs(4) |
Before
12/31/09
|
After
12/31/09
|
| Base
Fee for Debt Service (per ERU) |
$522
|
$522
|
| Use
Fee for O&M Costs (based on water use) |
$179
|
$179
|
| Total
Annual Costs |
$701
|
$701
|
(1) Cost of stub (or curb stop) is covered by funding for
customers signed up by December 31, 2009.
(2) Cost of connection is likely to be lower at time of water main installation.
(3) Paid through Rural Development funding for connected customers who sign up prior to December 31, 2009.
(4) Based on 280 ERUs connected to the water system.
|
Connection
Fee
A one-time
connection fee of $2,000 per ERU
will be charged for each new property to connect to the system.
A discounted connection fee of $500 per ERU will be
available for properties agreeing to connect before December 31,
2009. This includes the cost of the stub (or curb
stop) to the right-of-way, meter, pressure-reducing valves, backflow
prevention devices, associated fittings, and an allocation to a
maintenance reserve fund. This is possible because the stub
and appurtenances installed to the right-of-way during construction
will be subsidized by the grant funds. After December 31,
2009 customers will be responsible for all of those costs.
Cost
to Connect Service to Structure from Right-of-Way
Property
owners will be responsible for the cost to extend the water service
from the edge of the right-of-way to the building. This cost
will vary from property to property depending on the distance of
the structure from the edge of the right-of-way, obstacles such
as ledge or landscaping features, and who the property owner hires
to do the job. Generally, however, costs from $30 to $75 per
foot can be estimated. Customers whose properties are not
located on the same side of the road as the water line, and who
sign up after the project has gone out to bid, will also need pay
for the costs associated with boring under the sidewalk and Main
Street.
Funding
Sources
The funding
package secured through USDA Rural Development requires that the
entire cost of the municipal water project be borne by those connected
to the system and not the broader tax base. Thus, a town-wide
assessment to help offset the debt service would not
be an option.
Grants
& Loans
USDA
Rural Development. This federal agency has funded small
community water and wastewater projects in Vermont for decades.
Rural
Development (RD) typically offers a grant/loan package, with
the grant portion set as a function of local income level, expected
user rates, and funding availability. The Town did secure
a grant and loan package through RD of more than $5.5 million.
Vermont Agency of Natural Resouces. The Water
Supply Division of ANR administers a revolving loan fund (RLF)
for public water supply projects. Unfortunately, funding is
not available for construction because eligibility is limited to
existing water systems and not the development of new systems,
such as Waitsfield's. The Town was able to take advantage
of a planning RLF, which was used for the preliminary engineering
and source exploration phases of the project. Two 5-year,
no interest loans totaling $310,747 were obtained through the RLF,
with repayment slated to begin in 2012.
State and Tribal Assistance Grant (STAG). The Town
successfully applied for three earmarks totaling $3 million from
this federal program though the Vermont ANR and our Congressional
delegation. After administrative costs are subtracted, approximately
$2.9 million is available to be applied toward either the water
or wastewater projects. Approximatley $2 million has been
allocated to the water project, which will reimburse the Town for
up to 55% of the planning, design, and engineering costs incurred.
Other
Sources of Funding
Connection
Fees. Future connection fees will provide revenue to help
build a reserve fund and/or stabilize water rates.
Tax Increment Financing. Tax increment financing (TIF)
allows the Town to "divert" new tax revenue from
future developed properties within the district
to be spent on infrastructure within the district. The Town
continues to explore the use of this financing
tool to offset the debt service costs. If approved by
the state, approximately $2 million may be available during that
20-year period.
Costs
to Customers
The costs to
customers, both the on-going costs and the one-time connection costs,
will depend on a number of variables, including the number of ERUs
each property represents and distance of the structure from the
right-of-way (physical hook-up). Table
3 illustrates a potential scenario. As shown in Figure
1, the higher the number of connected users, the lower the costs.
Costs
to Non-Users in the Service Area
Connection to
the water system is voluntary. Properties not connected to
the system will not have any costs. The fire protection assessment
fee included with the original proposal that was voted down in March
2008 has been eliminated.
Costs
to Taxpayers
The Rural Development
funding package requires the project to paid for only by those connected
to the system. The cost
to taxpayers will be limited to the fees associated wtih municipal
buildings that connect to the system, such as the Town Office, Elementary
School, General Wait House, Fire Department, and Town Garage. If
the Town chooses not to connect any of its buildings to the system,
the cost to taxpayers for the water system would be zero.
Links
(Documents and
outside links will open in a separate window)
Contacts
Valerie J. Capels, Town Administrator
Waitsfield Town Office
9 Bridge Street
Waitsfield, VT 05673
Phone: (802) 496-2218
Fax: (802) 496-9284
E-mail: 
|
|
John Kiernan, Project Engineer
Phelps Engineering, Inc.
79 Court Street
P.O. Box 367 Middlebury, VT 05753
Phone: (802) 388-7829
Web: www.phelpseng.com |
Updated
October 8, 2009
|
Waitsfield's
Official Web Site
|
Please
send comments to: webmeister@waitsfieldvt.us
Copyright © 2007-2009 Town of Waitsfield, Vermont.
Hosted by http://www.networksolutions.com
|